Recent projects include:
·
A detailed analysis of intermittent control
sequence failures at a power plant. A brief study, identified a series of
small easily rectified faults. This solved the problem and avoided the expense of
replacing the existing control system.
·
The design of a site-wide industrial IT network
to integrate a new-build 90MW CCGT plant and related turn-key control packages
(DCS) with existing control and information systems.
·
Design and implementation of a new integrated
computerised control centre for the Manx Electricity Authority. The work
included full analysis of operator requirements, ergonomic
workstation design, integrated video wall display, common standards for
control screens, a viewing gallery and facilities for
crisis management. In addition to the operational requirements, the design
required a new IT infrastructure to accommodate over 30 computer systems and
servers away from the main operations areas.
·
The design of an integrated energy trading
system. This allowed traders and plant operators, at separate sites, to share
common real-time information on plant operation and electricity trades. A
centralised information database (MS-SQL) collects real-time meter readings and
commercial data from a variety of sources to provide an integrated history of
trading performance for billing reconciliation and cost analysis.